news

News

A First EPC Project in Europe: Xinhai Mining Delivers a CE-Compliant Galena–Fluorite Processing Plant in Italy

2026-02-05 Xinhai Views (15)

If you want to know more information, like quotation, products, solutions, etc., please contact us online.

Xinhai Mining has successfully delivered an EPC project for a 1,200 t/d galena–fluorite concentrator on the island of Sardinia, Italy. The project marks Xinhai’s first full EPC+M+O (Engineering, Procurement, Construction + Mine Management + Operation) contract completed in a developed European market, as well as the company’s 101st export destination worldwide.

More importantly, the project establishes Xinhai’s first fully CE-compliant EPC delivery framework, enabling the company to execute mineral processing projects in Europe in strict accordance with EU regulatory, safety, and environmental requirements. It represents a critical milestone in Xinhai Mining’s global expansion and long-term commitment to high-standard international markets.

Use the table of contents below to navigate through the guide:

01Process Design Tailored to Complex Galena–Fluorite Ore

The Sardinian deposit contains galena (PbS) and fluorite (CaF₂), with head grades of 1–3% PbS and 30–32% CaF₂. The concentrator is designed for a nominal capacity of 1,200 t/d, with 900 t/d allocated to grinding and flotation.

Given the high fluorite content and relatively low lead grade, the process was designed to recover coarse fluorite early through gravity pre-concentration, followed by preferential galena flotation and subsequent fluorite flotation. This approach maximizes overall recovery while maintaining high concentrate grades and stable operation.

porocess-design-tailored-to-complex-galena-fluorite-ore.jpg

Based on detailed metallurgical test work and Xinhai’s extensive experience in fluorite concentrator design, the final flowsheet comprises:

Crushing & Screening → Gravity Pre-Concentration → Desliming → Grinding & Classification → Lead Flotation → Fluorite Flotation → Concentrate Dewatering → Dry Tailings Disposal & Backfill

Key process features include:

02Stable Performance and Strong Technical Indicators

The plant has demonstrated stable operation and strong metallurgical performance, achieving the following key indicators:

Plant throughput

1,200 t/d

Grinding & flotation capacity

900 t/d

Head grade

 CaF₂ 30–32%; PbS 1–3%

Crushed product size

0–8 mm

Grinding fineness

60% −200 mesh

Regrinding fineness

93.5% −200 mesh

Concentrate grades

CaF₂ 98.06%; PbS 63.58%

Overall recovery

CaF₂ 68.3%; PbS 96.4%

Concentrate yield

Fluorite 21.59%; Galena 3.03%

With a lead recovery of 96.4% and a fluorite concentrate grade exceeding 98% CaF₂, the project significantly enhances the economic value of the ore while ensuring consistent product quality.

The adoption of dry stack tailings with underground backfill and 100% process water recycling enables near-zero discharge operation, fully aligned with EU environmental and sustainability expectations.

03CE Conformity: A Foundation for European EPC Delivery

A defining achievement of this project is Xinhai Mining’s first comprehensive implementation of CE conformity. CE marking (Conformité Européenne) is the EU’s mandatory regulatory framework governing safety, health, and environmental protection and is a prerequisite for market access across Europe.

For the Italian project, Xinhai conducted a complete CE assessment covering major processing equipment, structural components, and operating platforms. Particular emphasis was placed on safety-critical elements, including machine guarding, handrails, access systems, and protective structures. The process involved extensive technical documentation, risk assessment, and on-site verification in Italy.

Conformité-Européenne.jpg

The CE framework established through this project is fully documented and reusable, forming a standardized compliance pathway for future EU contracts. By completing on-site validation and regulatory alignment in Europe, Xinhai has effectively reduced technical and compliance barriers for subsequent projects in the region.

Compared with certification systems such as FCC in the United States, the CE system combines manufacturer self-declaration with third-party involvement for higher-risk products. Successful delivery under this framework demonstrates Xinhai Mining’s capability to integrate global compliance requirements into practical EPC execution.

04Strengthening Xinhai Mining’s Position in the European Market

The Sardinian galena–fluorite project represents more than a single successful delivery. It marks Xinhai Mining’s transition from an equipment and engineering exporter to a fully compliant EPC+M+O solution provider capable of operating within Europe’s regulatory and environmental framework.

With a proven CE-compliant EPC model, validated processes, and on-site execution experience in Europe, Xinhai Mining is now positioned to deliver future mineral processing projects with greater regulatory certainty, reduced delivery risk, and shorter implementation timelines.

xinhai-mining-in-talks-with-italian-clients.jpg

Xinhai Mining remains committed to providing integrated, end-to-end solutions worldwide—from metallurgical testing and process design to equipment supply, construction, commissioning, and long-term operation—supporting clients across the full lifecycle of their mining projects.

Xinhai Mining — your global partner for mineral processing and mine solutions.


RELATED PRODUCTS

RELATED NEWS

Contact Us

To find out more about our products and solutions, please fill out the form below and one of our experts will get back to you shortly.

  • Please fill in the Material

    • Gold
    • Silver
    • Copper
    • Iron
    • Lead
    • Zinc
    • Molybdenum
    • Chrome
    • Manganese
    • Nickel
    • Tin
    • Wolfram
    • Antimony
    • Barite
    • Fluorite
    • Feldspar
    • Graphite
    • Zircon
    • Lithium
    • Quartz
    • Others
xinhai