Zimbabwe 2400t/d Sand Chrome Processing Plant

According to the engineering project general contract, Xinhai provided mineral processing EPC+M+O service for this project.

Xinhai Solution

  • 01

    This project used washing - gravity separation process. 

  • 02

    Drum washing screen was used in washing process. The underflow of washing screen flew to the liner vibrating screen for classification. The materials on screen separated through jig and shaking table. The material material under screen entered the spiral chute divided into three levels. 

  • 03

    The concentrates of gravity separation flew to the sedimentation tank for dewatering.

  • 04

    The tailings were sent to the tailings pond by slurry pump.