PROJECT RESULT
Xinhai completed the construction drawing design within two months, from 18 March to 12 May 2021, and delivered the electronic drawings to the client on 27 May 2021, with printed drawings shipped together with the equipment. The thickening, filtration and magnetic separation equipment was supplied and installed on site under Xinhai's installation guidance, and the plant was put into operation by the end of 2024. The 480 t/d design capacity and the corresponding 158,400 t/a annual throughput are design values; no quantitative operating data is included in this case.