PROJECT RESULT
Construction drawing design was completed in December 2024 under a compressed schedule that ran from contract signature in July 2024. Equipment shipped in February 2025 and Xinhai's guidance team worked on site from May, completing installation guidance in September 2025. Built for 500 t/d with reserved space for 1,500 t/d, the plant gives the client a dedicated CIL route for recovering gold from purchased tailings, with wastewater, residue and exhaust treatment integrated into the design.