PROJECT RESULT
Construction drawings were submitted in March 2025, equipment shipped from March 2025 and installation ran from March to July 2025 across as many as five work fronts at peak. Most large equipment was shipped in sections and assembled on site, with mill transmission and cylinder aligned on centre lines and flotation cell surfaces levelled to tight tolerances. The plant is a benchmark project in northern Xinjiang that has drawn government visitors, and the completed expansion doubles the site's original grinding capacity within its existing footprint.