PROJECT RESULT
The engineering contract was signed in June 2023 and the full set of construction drawings was delivered on 30 November 2023 after revisions to place electrical cabinets in prefabricated cabins. Equipment was subsequently shipped and installation guidance began on site through 2025. Designed for 200 t/h within the 2 Mt/a limestone line, the plant applies a wet grinding and classification route that resolves the poor performance of earlier dry limestone powder preparation, supporting the client's downstream nickel processing.