Inner Mongolia 3,000t/d lead-zinc mineral tailings dry stacking plant was a tailings dry stacking project undertaken by Xinhai. Through the field investigation, Xinhai technicians made a series of program designs according to the output of tailings and the basic properties of tailings slurry, finally determined the appropriate tailings dry stacking process.
The tailings slurry was pumped into the XCII cyclone unit by the pump, and the cyclone underflow flowed to the high frequency dewatering screen. The oversize products were coarse dry tailings, which were transported to the tailings storage site by the belt conveyor. The overflow of cyclone unit entered the peripheral rack transmission thickener for concentration, the thickener underflow was pumped into the press filter by the slurry pump for pressure filtration, the filter cake was fine dry tailings, which was transported to the tailings storage site by the belt conveyor.
The undersize water was pumped into the thickener. The overflow of filtrate and thickener returned to the water recycling tank.
A new efficient thickening equipment independently developed by Xinhai.
A multifrequency dewatering screen with large capacity and full dehydration.
A hydrocyclone with involute feeding
A dewatering equipment that uses the slurry pump pressure to make liquid filter cloth come out, including chamber press filter and plate press filter