PROJECT RESULT
Construction drawing design began in August 2024 and was issued to the client in September 2024. The expanded line was commissioned in April 2025 and ran smoothly; by October 2025, the plant had reached an actual throughput of 850 t/d against its 800 t/d design basis, exceeding the target. The motors and reducers have held a zero-failure record since start-up, and the retrofit kept the original circuit producing throughout installation. This was the third plant project Xinhai delivered for the client, adding 300 t/d of capacity within the original footprint and reinforcing a long-running supply relationship.