PROJECT RESULT
The project moved from down payment to full expansion in just 10 months, running alongside the original 500t/d plant with zero shutdown. Upon commissioning, capacity quickly surpassed the 1200t/d design and stabilized at 1500t/d. Optimized grinding ensured consistently high recovery and leaching rates, while upgraded filtration and water systems boosted energy efficiency and environmental performance.Overall, the expansion delivered major gains in speed, capacity, efficiency, and operational reliability.